Funding :: DALLAS :: Project 20261 Details

TIP Code: 20261
CSJ: 0918-47-064
County: DALLAS
City: GARLAND
Agency: GARLAND
Project Type: BIKE/PEDESTRIAN
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: VA
Limits (from): MGR BIKEWAY FROM JUPITER & APOLLO
Limits (to): SOUTH CITY LIMITS AT DUCK CREEK
Scope of Work: CONSTRUCT BIKEWAY/TRAIL CONNECTING MESQUITE AND RICHARDSON, BRIDGE OVER DUCK CREEK, TRAIL CONNECTOR UNDER IH 30, DUCK CREEK GREENBELT, DUCK CREEK BRIDGE ADJACENT TO CENTERVILLE, ON/OFF STREET GLENBROOK/KINGSBRIDGE/APOLLO CONNECTOR, LINKS TO VELOWEB
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $3,620,086
091847064 Engineering $661,798
091847064 Construction $2,958,288
091847064 Construction Engineering $0
091847064 Contingencies $0
091847064 Indirect Costs $0
091847064 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $2,444,000 $1,176,086 $3,620,086
2012 ENG 091847064 RTR 121 - DA1 $0 $0 $661,798 $0 $661,798
2021 CON 091847064 RTR 121 - DA2 $0 $0 $1,782,202 $611,000 $2,393,202
2021 CON 091847064 Local Contribution $0 $0 $0 $565,086 $565,086

RTR Project Disbursements

TIP Advances Total Expenditures
  $0 $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2012 ENG 091847064 07/2012 07/2012 12/2019 07/2019
2021 CON 091847064 07/2020 11/2020 12/2021 12/2021

TIP 20261 Environmental Review Documents

No reports found

TIP 20261 Project Attachments