Funding :: COLLIN :: Project 20203 Details

TIP Code: 20203
CSJ: 0091-04-055, 0091-04-056
County: COLLIN
City: VARIOUS
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: SH 289
Limits (from): NORTH OF FM 1461/BS 289D
Limits (to): FM 455 IN CELINA
Scope of Work: RECONSTRUCT AND WIDEN 2 LANE RURAL HIGHWAY TO 4 LANE DIVIDED URBAN (ULTIMATE 6 LANES)
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $29,850,000
009104055 Engineering $2,000,000
009104055 Construction $23,950,075
009104055 Construction Engineering $0
009104055 Contingencies $0
009104055 Indirect Costs $0
009104055 Bond Financing $0
009104056 Right Of Way $3,899,925
009104056 Construction Engineering $0
009104056 Contingencies $0
009104056 Indirect Costs $0
009104056 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $2,000,000 $27,850,000 $6,420,844 $36,270,844
2010 ENG 009104055 SBPE $0 $2,000,000 $0 $0 $2,000,000
2010 ROW 009104056 RTR 121 - CC2 $0 $0 $3,899,925 $433,325 $4,333,250
2011 CON 009104055 RTR 121 - CC2 $0 $0 $23,950,075 $5,987,519 $29,937,594

RTR Project Disbursements

CSJ Total Expenditures
  $18,457,853  
009104055 $17,577,300  
009104056 $880,553  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2010 ENG 009104055 02/2010 02/2010 02/2011 02/2011
2010 ROW 009104056 02/2010 02/2010 04/2011 04/2011
2011 CON 009104055 07/2011 07/2011 08/2014 05/2015

TIP 20203 Environmental Review Documents

No reports found

TIP 20203 Project Attachments