Funding :: COLLIN :: Project 20202 Details

TIP Code: 20202
CSJ: 0091-04-050, 0091-04-057
County: COLLIN
City: PROSPER
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: SH 289
Limits (from): US 380 INTERCHANGE
Limits (to): NORTH OF FM 1641/BS 289D
Scope of Work: RECONSTRUCT AND WIDEN TWO LANE RURAL HIGHWAY TO SIX LANE DIVIDED URBAN ROADWAY
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $30,817,349
009104050 Utilities $106,250
009104050 Construction $20,405,172
009104050 Construction Engineering $1,168,269
009104050 Contingencies $1,687,500
009104050 Indirect Costs $1,269,519
009104050 Bond Financing $0
009104057 Right Of Way $6,180,639
009104057 Construction Engineering $0
009104057 Contingencies $0
009104057 Indirect Costs $0
009104057 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $25,647,878 $1,044,183 $26,692,061
2011 ROW 009104057 RTR 121 - CC2 $0 $0 $5,562,878 $617,761 $6,180,639
2011 UTIL 009104050 RTR 121 - CC2 $0 $0 $85,000 $21,250 $106,250
2011 CON 009104050 RTR 121 - CC2 $0 $0 $20,000,000 $405,172 $20,405,172

RTR Project Disbursements

CSJ Total Expenditures
  $19,511,624  
009104050 $17,182,195  
009104057 $2,329,429  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2011 ROW 009104057 01/2011 01/2011 07/2011 07/2011
2011 UTIL 009104050 01/2011 01/2011 07/2011 07/2011
2011 CON 009104050 07/2011 07/2011 08/2014 03/2015

TIP 20202 Environmental Review Documents

No reports found

TIP 20202 Project Attachments