Funding :: DALLAS :: Project 20132 Details

TIP Code: 20132
CSJ: 0918-47-004
County: DALLAS
City: VARIOUS
Agency: DALLAS CO
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): ON MILLER ROAD FROM GARLAND EAST CITY LIMITS
Limits (to): ROWLETT WEST CITY LIMITS
Scope of Work: 2 LANE ASPHALT SECTION TO 4 LANE DIVIDED CONCRETE SECTION
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $12,436,870
091847004 Engineering $1,966,262
091847004 Right Of Way $58,493
091847004 Utilities $250,000
091847004 Construction $10,162,115
091847004 Construction Engineering $0
091847004 Contingencies $0
091847004 Indirect Costs $0
091847004 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $9,949,496 $2,487,374 $12,436,870
2010 ENG 091847004 RTR 121 - DA1 $0 $0 $1,573,010 $393,252 $1,966,262
2013 ROW 091847004 RTR 121 - DA1 $0 $0 $46,794 $11,699 $58,493
2013 UTIL 091847004 RTR 121 - DA1 $0 $0 $200,000 $50,000 $250,000
2014 CON 091847004 RTR 121 - DA1 $0 $0 $8,129,692 $2,032,423 $10,162,115

RTR Project Disbursements

TIP Advances Total Expenditures
  $0 $0  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2010 ENG 091847004 04/2010 04/2010 04/2013 04/2013
2013 ROW 091847004 04/2013 04/2013 09/2013 09/2013
2013 UTIL 091847004 04/2013 04/2013 09/2013 09/2013
2014 CON 091847004 10/2013 10/2013 06/2016 05/2017