Funding :: DENTON :: Project 20109 Details

TIP Code: 20109
CSJ: 0619-05-034, 0619-05-035
County: DENTON
City: CARROLLTON
Agency: TXDOT-DALLAS
Project Type: ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: FM 544
Limits (from): FM 2281 (DENTON DRIVE)
Limits (to): 0.17 MILES WEST OF JOSEY LANE
Scope of Work: RECONSTRUCT AND WIDEN TWO LANE RURAL HIGHWAY TO SIX LANE DIVIDED URBAN FACILITY
Comments: RTR 121-DE1 FUNDS; LOCAL CONTRIBUTION PAID BY DENTON COUNTY

Total Project Cost

CSJ Phase Total Project Cost
Total: $41,595,148
061905034 Engineering $6,135,952
061905034 Utilities $888,889
061905034 Construction $23,137,241
061905034 Construction Engineering $1,061,781
061905034 Contingencies $425,997
061905034 Indirect Costs $1,228,755
061905034 Bond Financing $0
061905035 Right Of Way $6,000,000
061905035 Construction Engineering $1,061,781
061905035 Contingencies $425,997
061905035 Indirect Costs $1,228,755
061905035 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $3,200,000 $800,000 $25,671,113 $6,490,969 $36,162,082
2013 ENG 061905034 RTR 121 - DE1 $0 $0 $333,872 $0 $333,872
2013 ENG 061905034 Local Contribution $0 $0 $0 $5,802,080 $5,802,080
2013 ROW 061905035 RTR 121 - DE1 $0 $0 $5,400,000 $600,000 $6,000,000
2015 UTIL 061905034 RTR 121 - DE1 $0 $0 $800,000 $88,889 $888,889
2015 CON 061905034 RTR 121 - DE1 $0 $0 $19,137,241 $0 $19,137,241
2015 CON 061905034 7 - STP-MM $3,200,000 $800,000 $0 $0 $4,000,000

RTR Project Disbursements

CSJ Total Expenditures
  $20,873,670  
061905034 $17,577,239  
061905035 $3,296,430  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2013 ENG 061905034 07/2012 08/2005 06/2014 08/2014
2013 ROW 061905035 07/2012 07/2012 06/2014 01/2013
2015 UTIL 061905034 06/2014 09/2014 09/2018 08/2016
2015 CON 061905034 06/2014 09/2014 04/2020 04/2020

TIP 20109 Environmental Review Documents

No reports found