Funding :: DENTON :: Project 20108 Details

TIP Code: 20108
CSJ: 0918-46-238
County: DENTON
City: LEWISVILLE
Agency: LEWISVILLE
Project Type: NEW ROADWAY, ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): ON CORPORATE DR FROM HOLFORD'S PRAIRIE RD
Limits (to): ELM FORK TRINITY RIVER BRIDGE
Scope of Work: CONSTRUCT FOUR LANE DIVIDED ROADWAY; SEGMENT 4
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $16,143,643
091846238 Engineering $641,389
091846238 Right Of Way $1,281,220
091846238 Construction $13,580,000
091846238 Construction Engineering $404,219
091846238 Contingencies $0
091846238 Indirect Costs $236,815
091846238 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $10,086,038 $5,416,571 $15,502,609
2015 ENG 091846238 RTR 121 - DE1 $0 $0 $513,111 $128,278 $641,389
2019 ROW 091846238 RTR 121 - DE1 $0 $0 $1,024,976 $256,244 $1,281,220
2022 CON 091846238 RTR 121 - DE1 $0 $0 $8,547,951 $2,136,988 $10,684,939
2022 CON 091846238 Local Contribution $0 $0 $0 $2,895,061 $2,895,061

RTR Project Disbursements

TIP Advances Total Expenditures
  $8,166,038 $1,187,375  
20108.00 $8,166,038 $1,187,375  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2015 ENG 091846238 07/2014 12/2014 07/2022
2019 ROW 091846238 06/2018 03/2019 03/2022
2022 CON 091846238 12/2022 12/2025

TIP 20108 Environmental Review Documents

No reports found

TIP 20108 Project Attachments