Funding :: COLLIN :: Project 20083 Details

TIP Code: 20083
CSJ: 2679-02-008, 2679-02-009
County: COLLIN
City: PARKER
Agency: TXDOT-DALLAS
Project Type: INTERSECTION IMPROVEMENT, BIKE/PEDESTRIAN, ADDITION OF LANES
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: FM 2514
Limits (from): FM 2551
Limits (to): WEST OF FM 1378
Scope of Work: WIDEN 2 LANE RURAL TO 4 LANE (ULTIMATE 6 LANE) URBAN ROADWAY INCLUDING NEW PEDESTRIAN IMPROVEMENTS AND LEFT/RIGHT TURN LANES
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $29,072,189
267902008 Engineering $950,000
267902008 Construction $18,217,689
267902008 Construction Engineering $858,009
267902008 Contingencies $344,241
267902008 Indirect Costs $0
267902008 Bond Financing $0
267902009 Right Of Way $7,500,000
267902009 Construction Engineering $858,009
267902009 Contingencies $344,241
267902009 Indirect Costs $0
267902009 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $17,841,600 $4,410,400 $3,415,689 $1,000,000 $26,667,689
2013 ENG 267902008 Local Contribution $0 $0 $0 $250,000 $250,000
2013 ENG 267902008 SBPE $0 $700,000 $0 $0 $700,000
2013 ROW 267902009 S102 $6,000,000 $750,000 $0 $750,000 $7,500,000
2018 CON 267902008 RTR 121 - CC1 $0 $0 $3,415,689 $0 $3,415,689
2018 CON 267902008 2M - METRO CORR $10,880,000 $2,720,000 $0 $0 $13,600,000
2018 CON 267902008 5 - CMAQ $961,600 $240,400 $0 $0 $1,202,000

RTR Project Disbursements

CSJ Total Expenditures
  $2,365,904  
267902008 $2,365,904  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2013 ENG 267902008 08/2013 08/2013 04/2018 06/2018
2013 ROW 267902009 08/2013 08/2013 07/2018 06/2017
2018 CON 267902008 05/2018 06/2018 08/2021 04/2021

TIP 20083 Environmental Review Documents

No reports found

TIP 20083 Project Attachments