Funding :: DALLAS :: Project 11747 Details

TIP Code: 11747
CSJ: 0918-47-015
County: DALLAS
City: VARIOUS
Agency: DALLAS CO
Project Type: INTERSECTION IMPROVEMENT
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): WINTERGREEN ROAD FROM DUNCANVILLE ROAD EAST OF STEWART BRANCH CREEK
Limits (to): AND DUNCANVILLE ROAD FROM WINTERGREEN TO SOUTH OF STEWART BRANCH CREEK
Scope of Work: REALIGN OFFSET INTERSECTION TO ACCOMMODATE 4 LANE APPROACHES
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $8,199,000
091847015 Engineering $1,630,000
091847015 Right Of Way $625,000
091847015 Construction $5,944,000
091847015 Construction Engineering $0
091847015 Contingencies $0
091847015 Indirect Costs $0
091847015 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $0 $3,130,000 $5,069,000 $8,199,000
2009 ENG 091847015 RTR 121 - DA1 $0 $0 $960,000 $240,000 $1,200,000
2009 ENG 091847015 Local Contribution $0 $0 $0 $430,000 $430,000
2016 ROW 091847015 Local Contribution $0 $0 $0 $625,000 $625,000
2019 CON 091847015 RTR 121 - DA1 $0 $0 $2,170,000 $542,500 $2,712,500
2019 CON 091847015 Local Contribution $0 $0 $0 $3,231,500 $3,231,500

RTR Project Disbursements

TIP Advances Total Expenditures
  $3,131,045 $44,330  
11747.00 $3,131,045 $44,330  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2009 ENG 091847015 04/2010 04/2009 01/2018 02/2018
2016 ROW 091847015 06/2016 04/2016 05/2018 05/2018
2019 CON 091847015 01/2019 01/2019 11/2021 02/2022

TIP 11747 Environmental Review Documents

No reports found