Funding :: TARRANT :: Project 11262.2 Details

TIP Code: 11262.2
CSJ: 0902-90-070
County: TARRANT
City: FORT WORTH
Agency: FORT WORTH
Project Type: NEW ROADWAY, BIKE/PEDESTRIAN
On System:
Advance:
Loan:
  • Before Image
  • Profile image
  • After Image
  • Profile image

Location

Facility Name: CS
Limits (from): LANCASTER AVE; ON HEMPHILL/LAMAR CONNECTOR
Limits (to): VICKERY BLVD
Scope of Work: CONSTRUCT 0 TO 4 LANE DIVIDED ROAD UNDER UPRR & IH 30; INCLUDES TURN LANES, BIKE/PED SHARED PATH, SIGNAL, ILLUMINATION, SIGNAGE, LANDSCAPING, RAIL BRIDGE, AND RAIL SHOOFLY
Comments:

Total Project Cost

CSJ Phase Total Project Cost
Total: $53,682,421
090290070 Engineering $2,174,986
090290070 Right Of Way $10,356,000
090290070 Construction $40,610,000
090290070 Construction Engineering $145,400
090290070 Construction Engineering $145,400
090290070 Contingencies $250,635
090290070 Indirect Costs $0
090290070 Bond Financing $0

Funding Information

Fiscal Year Phase CSJ Category Federal State Regional Local Total
        $0 $145,400 $3,448,803 $49,692,183 $53,286,386
2015 ROW 090290070 Local Contribution $0 $0 $0 $10,356,000 $10,356,000
2017 ENG 090290070 Local Contribution $0 $0 $0 $2,174,986 $2,174,986
2017 CON 090290070 RTR 121 - TC1 $0 $0 $3,448,803 $0 $3,448,803
2017 CON 090290070 Local Contribution $0 $0 $0 $37,161,197 $37,161,197
2017 CONENG 090290070 SBPE $0 $145,400 $0 $0 $145,400

RTR Project Disbursements

TIP Advances Total Expenditures
  $3,448,803 $3,448,803  
11262.20 $3,448,803 $3,448,803  

Status

Fiscal Year Phase CSJ Est Let Act Let Est Compl Act Compl
2015 ROW 090290070 11/2017 01/2015 04/2018 06/2015
2017 ENG 090290070 09/2017 03/2017 12/2017 06/2017
2017 CON 090290070 06/2018 06/2017 03/2020 04/2020
2017 CONENG 090290070 06/2018 06/2017 03/2020 04/2020

TIP 11262.2 Environmental Review Documents

No reports found

TIP 11262.2 Project Attachments